Project Schedule:

  • Start construction of new addition - January 2003
    • OR occupancy: December 6, 2004
    • CSS occupancy: December 12, 2004
    • Clinical Labs occupancy: May 6, 2005
    • Morgue/Autopsy occupancy: May 6, 2005
    • Heart Center Offices occupancy: June 6, 2005
    • Interventional Radiology occupancy:  July 28, 2005
  • New addition complete - August 2005
  • Start lobby renovations - Summer 2003
    • Occupancy: July 31, 2004
  • Start second floor renovations -  January 2005
  • Construction complete - December 2006